Kamran Construction v. Nazir Talib

Contract lawSupreme Court of Pakistan · 2010 SCMR 829

Damages, restitution and commercial security

Held

Under section 73 the claimant must plead and prove breach, resulting loss and quantum. Later advertisements do not add terms to an earlier contract without incorporation.

Facts

A flat purchaser obtained possession, specific performance and monthly damages for delay. The builder contested the damages and accepted its obligation to deliver the flat.

Ruling

The Court set aside the damages award and directed prompt execution of the decree for possession and specific performance.

Reasoning

The later advertisements did not establish the builder’s obligations under this purchase. The evidence did not support the monthly sum awarded.