Mst. Amina Bibi v. Mudassar Aziz

Contract lawSupreme Court of Pakistan · PLD 2003 SC 430

Performance, reciprocal obligations and time

Held

A party who prevents timely completion cannot rely on the resulting delay. Intention to make time essential must be clear.

Facts

A vendor resisted specific performance of a residential plot agreement after failing to obtain the housing society’s permission required for transfer.

Ruling

The appeal was dismissed and the decree for specific performance remained in force.

Reasoning

The purchaser could not complete the transaction while the vendor’s prerequisite remained outstanding. The agreed sequence of performance determined responsibility for delay.