Mst. Amina Bibi v. Mudassar Aziz
Performance, reciprocal obligations and time
Held
A party who prevents timely completion cannot rely on the resulting delay. Intention to make time essential must be clear.
Facts
A vendor resisted specific performance of a residential plot agreement after failing to obtain the housing society’s permission required for transfer.
Ruling
The appeal was dismissed and the decree for specific performance remained in force.
Reasoning
The purchaser could not complete the transaction while the vendor’s prerequisite remained outstanding. The agreed sequence of performance determined responsibility for delay.