Mst. Samina Riffat v. Rohail Asghar

Contract lawSupreme Court of Pakistan · 2021 SCMR 7

Performance, reciprocal obligations and time

Held

Express cancellation and forfeiture terms can take effect where the purchaser defaults and fails to establish readiness.

Facts

A purchaser missed the agreed payment deadline and failed to deposit the balance despite a court direction. The High Court nevertheless ordered repayment of earnest money with profit.

Ruling

The Court allowed the appeal with a modification. Each appellant was to refund Rs. 500,000 under a voluntary concession.

Reasoning

The terms specified the consequences of default and the purchaser’s conduct showed lack of capacity or readiness. The half-refund followed the concession made in this case.

Read the judgment

Facing a similar issue? Request a legal opinion from Wajid Munir Abbasi, Advocate High Court.

Case note for general information only, not legal advice. Check the official report before relying on it.